METHOD OF STATEMENT FOR BREAKING PILE

WORK METHODOLOGY
  1. Mark the correct cutting level using survey instrument and marking at least 4 centimeters into the desired level.
  2. Break the pile using large jackhammers up to 100 millimeters above the marked level.
  3. Break the remaining pile head by small electric jackhammers and flatten it to the correct level. Chipping of small loose concrete to be done manually by hammer and chisel.
  4. Finally all pile reinforcement shall be cut to the required development length and all reinforcement with development length shall be spliced with couplers.