WORK METHODOLOGY
- Mark the correct cutting level using survey instrument and marking at least 4 centimeters into the desired level.
- Break the pile using large jackhammers up to 100 millimeters above the marked level.
- Break the remaining pile head by small electric jackhammers and flatten it to the correct level. Chipping of small loose concrete to be done manually by hammer and chisel.
- Finally all pile reinforcement shall be cut to the required development length and all reinforcement with development length shall be spliced with couplers.
Teraju A&S Bina Sdn. Bhd.
No. 5-5A, Jalan Kirana 1,
Taman Kirana,
86100 Ayer Hitam,
Johor Darul Takzim.
Tel : 018-580 1703 / 07-758 2922 / 07-758 2722
Fax : 07-758 2216
Email : terajuansbina7878@gmail.com
https://www.facebook.com/TerajuBina Sdn Bhd
http://www.terajuansbina7878.wix.com/tasb
No. 5-5A, Jalan Kirana 1,
Taman Kirana,
86100 Ayer Hitam,
Johor Darul Takzim.
Tel : 018-580 1703 / 07-758 2922 / 07-758 2722
Fax : 07-758 2216
Email : terajuansbina7878@gmail.com
https://www.facebook.com/TerajuBina Sdn Bhd
http://www.terajuansbina7878.wix.com/tasb
No comments:
Post a Comment